Proponent: Exploits Valley Renewable Energy Corporation (EVREC)
Summary of Environmental Assessment Process
Project Description:
The Proponent is proposing to construct and operate a 3.5 gigawatt (GW) onshore wind energy project consisting of three wind farms with up to 530 turbines in the Central Newfoundland area, and a 150-megawatt solar farm and a 2.6 GW hydrogen/ammonia production facility in Botwood.
- October 7, 2024 – The undertaking was registered.
- November 11, 2024 – Deadline for public comments.
- November 21, 2024 – The Minister’s decision is due.
- December 6, 2024 – The Minister’s decision is due (extended).
- December 5, 2024 – The Minister determined that an Environmental Impact Statement (EIS) is required, and an Environmental Assessment Committee is appointed.
- April 4, 2025 – EIS Guidelines due to be issued.
- February 13, 2025 – Draft EIS Guidelines for public review.
- March 26, 2025 – Deadline for public comments on Draft EIS Guidelines.
- April 2, 2025 – Approved EIS Guidelines Issued.
- Documents:
- Registration Document (3 MB)
- Appendix A – Drawings 1.1-3.8 (20 MB)
- Appendix A – Drawings 3.9-3.22 (16 MB)
- Appendices B – F (5 MB)
- Appendix B – CO2 Summary From EVREC
- Appendix C – Atlantic Canada Conservation Data Centre (ACCDC) Report
- Appendix D – Archaeology Report
- Appendix E – Public Meetings/Information Sessions
- Appendix F – Environmental Protection Plan (EPP) Table of Contents.
- Decision Letter (EIS Required and EAC Appointed) (102 KB)
- DRAFT EIS Guidelines (667 KB)
- Decision Letter (Approved EIS Guidelines) (36 KB)
- Approved EIS Guidelines (703 KB)
- Registration Document (3 MB)
- Public Notices:
- Project Registered (85 KB)
- EIS Required and EAC Appointed (105 KB)
- DRAFT EIS Guidelines for Public Review (90 KB)
- Approved EIS Guidelines Issued (91 KB)
Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free