PROPONENT: Trinity Resources Limited
Summary of Environmental Assessment Process
Project Description:
The proponent is proposing to install a processing facility at its existing mine site that would separate mined and stockpiled ore into various products. The processing facility would allow a complete reclamation of existing stockpiles and would eliminate future stockpiles from being created during mine development. Active mining operations in the Oval Pit and Mine Hill deposits would be re-established and a 1.3 kilometre by-pass road would be constructed.
- September 28, 2022 – The undertaking was registered.
- November 3, 2022 – Deadline for public comments.
- November 12, 2022 – The Minister’s decision is due.
- November 25, 2022 – The Minister’s decision is due (extended).
- December 9, 2022 – The Minister’s decision is due (extended).
- December 9, 2022- The Minister determined the project is released.
- Documents:
- Registration Document (6 MB)
- Appendix (2 MB)
- Decision Letter (4 MB)
- Public Notices:
- Project Registered (121 KB)
- Project Released (109 KB)
Adobe® Acrobat® Reader software can be used for viewing PDF documents. Download Acrobat® Reader for free