Registration Number: 2322

Blaketown to Riverhead 94L Transmission Line Rebuild

Proponent: Newfoundland Power

Summary of Environmental Assessment Process

Project Description:

The Proponent is proposing a revision to its project (Registration #2184) that was released from further environmental assessment in January 2022. The revised work would involve the rerouting of a section of their 94L Transmission Line between the communities of Blaketown and Riverhead to avoid sensitive wetlands.

  • September 17, 2024 – The undertaking was registered.
  • October 25, 2024 – Deadline for public comments.
  • November 1, 2024 – The Minister’s decision is due.
  • November 15, 2024 – The Minister’s decision is due (extended).
  • November 20, 2024 – The Minister determined the Project is released.