Proponent: Argentia Renewables Wind LP
Summary of Environmental Assessment Process
Project Description:
The Proponent is proposing to construct and operate a 300 megawatt (MW), 46-turbine onshore wind farm in the Placentia area with the associated transmission and supporting infrastructure to power a 160 MW hydrogen/ammonia production facility in the Port of Argentia.
- August 1, 2024 – The undertaking was registered.
- September 5, 2024 – Deadline for public comments.
- September 15, 2024 – The Minister’s decision is due.
- September 20, 2024 – The Minister’s decision is due (extended).
- September 19, 2024 – Environmental Preview Report (EPR) is required.
- November 18, 2024 – The EPR Guidelines are due to be issued.
- December 2, 2024 – The EPR Guidelines are due to be issued (extended).
- December 13, 2024 – The EPR Guidelines are due to be issued (extended).
- December 13, 2024 – EPR Guidelines issued.
- November 21, 2024 – The project has been withdrawn by the proponent.
- Documents:
- Registration Document (60 MB)
- Appendices:
- Appendix A – Atmospheric Environment Baseline Study (2.8 MB)
- Appendix B1 and B2 (29.2 MB)
- B1 – Aquatic Baseline Study
- B2 – Dispersion Study
- Appendix C1 and C2 (18.9 MB)
- C1 – Source Water Hydrology Study
- C2 – Water Management and Monitoring Plan
- Appendix D1 – D7 (16 MB)
- D1 – Avifauna Baseline Study
- D2 – Bat Baseline Study
- D3 – Ecological Land Classification Baseline Study
- D4 – Mammals Baseline Study
- D5 – Rare Lichen Baseline Study
- D6 – Rare Plants Baseline Study
- D7 – Insects Baseline Study
- Appendix E-H (17.8 MB)
- E – Transportation Impact Study and Transportation Management Plan
- F – Historic Resources Overview
- G – Socio-Economic Baseline
- H – Energy and Emissions Study
- Appendix I-L (42 MB)
- I – Light Impact Assessment
- J – Noise and Vibration Impact Study
- K – Shadow Flicker Impact Assessment
- Appendix M-T (10.3 MB)
- M – Emergency Response and Contingency Plan
- N – Waste Management Plan
- O – Hazardous Material Training Plan
- P – Public Participation Plan
- Q – Workforce and Employment Plan
- R – Species at Risk Impacts Mitigation and Monitoring Plan
- S – Bat and Avian Post-construction Monitoring Plan
- T – Domestic Woodcutting Consultation Plan
- Appendix U1 – U4 (64.3 MB)
- U1 – Public Information Session Material, October 26, 2022
- U2 – Public Information Session Material, February 27, 2023
- U3 – Public Information Session Material, November 16, 2023
- U4 – Public Information Session Material, June 3, 2024
- Appendix V-W (2.9 MB)
- V – Risk Assessment Workshop Report
- W – Mitigation Measures
- Decision Letter (555 KB)
- Decision Letter – EPR Guidelines Issued (31 KB)
- EPR Guidelines (262 KB)
- Public Notices:
- Project Registered (113 KB)
- EPR Required (140 KB)
- EPR Guidelines Issued (97 KB)
- Project Withdrawn (90 KB)