Project Description:

The proponent is proposing to construct and operate a 324 megawatt (MW) onshore wind energy project consisting of 45 turbines in the Sunnyside area, a Hydrogen Generation Plant (HGP) capable of producing 30,000 tonnes per annum (tpa) of hydrogen, and a Hydrogenation Plant (HP) capable of processing 60,000 tpa of hydrogen at the existing Come by Chance terminal.

  • July 17, 2025 – The undertaking was registered.
  • August 21, 2025 – Deadline for public comments.
  • August 31, 2025 – The Minister’s decision is due.
  • September 2, 2025 – Environmental Preview Report (EPR) is required.
  • September 2, 2025 – Environmental Assessment Committee (EAC) appointed.
  • November 1, 2025 – The EPR Guidelines are due to be issued.
  • November 6, 2025 – EPR Guidelines issued.